Construction of LĪPOA’s newest subdivision is making progress to the south of Lipoa Parkway. Goodfellow Bros. has been working to complete infrastructure improvements that will provide access and utilities to the three newly created commercial lots.

Work is currently underway to extend underground infrastructure and utilities including waterlines, drainage systems, and electrical and telecommunications within South Ninau Street and South Holopono Street. Following installation of the utilities, the roadway extension work – that will extend South Ninau and South Holopono Streets approximately 600 feet – is targeted to begin in
January 2024.

The paving of these roadway extensions is planned for February 2024, with completion of the project on track for March 2024.